Overview

The purpose of this standard is to provide the candidate with the knowledge to point and joint in façade preservation.

Duration

Minimum 1 day of 6 learning hours

Purpose/ scope

The purpose of this standard is to provide the candidate with the knowledge to point and joint in façade preservation.

The scope of this standard covers:

  • job specifications
  • personal protective equipment (PPE), respiratory protective equipment (RPE), and safety controls
  • hand and power tools
  • signage, protections, and barriers
  • mortar specifications
  • rake out mortar
  • prepare for pointing
  • point a test area
  • how to point
  • work safely
  • local authority recycling/waste management

Occupational relevance

Training delivered against this standard would be relevant to the following occupational group(s):

  • operative and craft

Candidate pre-requisites

There are no candidate pre-requisites as part of this standard.

Before candidates perform facade work at height on a construction site, candidates must have successfully completed specific training for working safely at height.

Instruction/ supervision

As a minimum, course instructors must be able to demonstrate that, in relation to this standard, they have:

  • a train the trainer or instructional techniques course certificate
  • successfully completed training to this standard
  • at least 2 years relevant industrial experience
  • a verifiable CV

Delivery

The following method(s) may be used in the delivery of this standard:

  • classroom

All materials and equipment must be of a suitable quality and quantity for candidates to achieve learning outcomes, and must comply with relevant legislation.

The class size and candidate/instructor ratio must allow training to be delivered in a safe manner and enable candidates to achieve the learning outcomes.

Assessment

For the successful completion of training, candidates must complete an end of course practical assessment or knowledge test that measures the learning outcomes and has a pass or fail criteria.

Quality assurance

Quality assurance against this standard will require initial approval of the training organisation and their content mapped to the standard.

CITB will also conduct an approval intervention, either desk-based or centre visit, to ensure the training organisation can meet the requirements of the training standard.

Approved training organisations (ATOs) will be required to present information on records of training and assessment upon request to CITB for desk based analysis. They will also be visited annually by the CITB quality assurance team.

Renewal

No renewal/refreshment requirements - There are no mandatory renewal or recommended refreshment requirements for this standard.

Approval date

November 2018

Review cycle

Either on request or in 3 years from approval date (of the standard)

Learning outcomes

The candidate will be able to:

  • Describe how to interpret job specifications
  • Describe how to select, use, maintain, and store PPE, RPE, and safety controls
  • Describe how to select, use, maintain, and store hand and power tools
  • Describe how to select and install: signage, protections and barriers
  • Interpret mortar specifications for repairing façades
  • Describe how to rake out mortar
  • Describe how to prepare for pointing
  • Describe how to point a test area
  • Describe how to point

Additional guidance to support learning outcome

Examples of:

  • job specifications
  • construction drawings

Videos of good and bad practice

Examples of tools and equipment

The candidate will be able to:

Describe how to work safely including:

  • follow safe work practices/procedures
  • location of emergency procedures
  • identify hazards
  • reduce/eliminate risks
  • use controls
  • use PPE
  • specific hazards include: water, chemicals, barriers, heights, work platforms, slip, trip, fall, dust, vibration, noise, reduced vision, sharp edges, hot parts, pressurised liquid, abrasives, air pressure valve
  • keep a clean and tidy work area
  • earth leakage protection (residual current device, RCD)
  • extension and power leads (connectors, trips, testing)
  • petrol/diesel fuel (fire, fumes, spills)
  • first aid equipment
  • environmental safety

Additional guidance to support learning outcome

Examples of:

  • PPE
  • risk assessments
  • safe work practices/procedures
  • spills and clean up
  • environmental legislation
  • safety legislation
  • SDS sheets for COSHH
  • RAMS
  • first aid equipment

The candidate will be able to:

Describe how to confirm and comply with local authority recycling/waste management 

Additional guidance to support learning outcome

  • Environmental considerations for waste materials

Additional information about this standard

Heritage

HSE Water jetting guides

Training at height

  • BS 8454:2006 Code of practice for delivery of training & education for work at height and rescue

Advisory Committee for Roof Safety

Work at Height Safety Association

  • The WAHSA technical guidance notes are a free resource, provided and maintained by WAHSA and its member companies for reference. They assist specifiers, managers, and end users of fall protection equipment. http://www.wahsa.org.uk/technical-guidance/

Health & Safety Executive (HSE) Working at height guides

  • Working at height: http://www.hse.gov.uk/work-at-height/resources.htm
  • Useful web links on working at height: http://www.hse.gov.uk/work-at-height/links.htm
  • Health and safety in roof work: http://www.hse.gov.uk/pubns/priced/hsg33.pdf
  • Working on roofs: http://www.hse.gov.uk/pubns/indg284.pdf
  • Fragile roofs, safe working practices: http://www.hse.gov.uk/pubns/geis5.pdf

HSE guides

  • Health & Safety at Work etc Act 1974: http://www.hse.gov.uk/legislation/hswa.htm
  • Health and safety in construction: http://www.hse.gov.uk/construction/index.htm
  • Personal protective equipment a brief guide: http://www.hse.gov.uk/pubns/indg174.pdf
  • PPE: http://www.hse.gov.uk/toolbox/ppe.htm
  • PUWER: http://www.hse.gov.uk/work-equipment-machinery/puwer.htm
  • COSHH: http://www.hse.gov.uk/coshh
  • RIDDOR: http://www.hse.gov.uk/riddor/
  • LOLER: http://www.hse.gov.uk/work-equipment-machinery/loler.htm
  • CDM: http://www.hse.gov.uk/construction/cdm/2015/index.htm
  • Manual handling: http://www.hse.gov.uk/toolbox/manual.htm
  • Noise: http://www.hse.gov.uk/noise/index.htm
  • Hand-arm vibration: www.hse.gov.uk/vibration/hav/index.htm
  • Electrical: http://www.hse.gov.uk/electricity/hse.htm

Legislation

http://www.legislation.gov.uk/

  • Health and Safety at Work etc Act (HSWA) 1974
  • The Work at Height Regulations (WHR) 2005
  • Work at Height (Amended) 2007
  • Personal Protection Equipment (PPE) Regulations 2002
  • Personal Protection Equipment (PPE) at Work Regulations 1992
  • Provision and Use of Work Equipment Regulations (PUWER) (1998 UK 1999 NI)
  • Control of Substances Hazardous to Health Regulations (COSHH )2002
  • Lifting Operations and Lifting Equipment Regulations (LOLER) 1998
  • Reporting of Injuries, Diseases and Dangerous Occurrences Regulations (RIDDOR ) 1995
  • Construction (Design and Management) Regulations (CDM) 2015
  • Construction (Health, Safety and Welfare) Regulations 1996
  • Manual Handling Operations Regulations 1992 as amended 2002
  • Control of Noise at Work Regulations 2005
  • Control of Vibration at Work Regulations 2005

Building regulations

  • Building and Buildings, England and Wales: The Building Regulations 2010.
  • The Building (Scotland) Regulations 2004
  • Statutory Rules of Northern Ireland

British standards

https://shop.bsigroup.com/en/

  • BS 8000: 2013 Workmanship on construction sites.
  • BS 8437: 2005 Code of practice for selection, use and maintenance of personal protection systems
  • BS EN 12810-1:2003. Facade scaffolds made of prefabricated components. Product specifications
  • BS EN 12810-2:2003. Facade scaffolds made of prefabricated components. Structural design
  • BS EN 12811-1:2003. Temporary works equipment. Scaffolds. Performance and general design